''Illustrative model. Spektrum built this site from published sources to show how a Development by Consent process about the future of the Cobre Panamá mine could work. No such process has been agreed: not by the Government of Panama, not by First Quantum Minerals, and not by any community. Nothing here speaks for them.''
''Illustrative model. Spektrum built this site from published sources to show how a Development by Consent process about the future of the Cobre Panamá mine could work. No such process has been agreed: not by the Government of Panama, not by First Quantum Minerals, and not by any community. Nothing here speaks for them.''



Latest revision as of 12:21, 17 November 2026

Illustrative model. Spektrum built this site from published sources to show how a Development by Consent process about the future of the Cobre Panamá mine could work. No such process has been agreed: not by the Government of Panama, not by First Quantum Minerals, and not by any community. Nothing here speaks for them.

Since the closure, two kinds of activity have been approved at the site. Neither is a decision to reopen the mine.

Preservation and safe management

On 30 May 2025 the company said the Government had approved a Preservation and Safe Management programme, with environmental measures at the site, paid for by exporting 121,000 dry metric tonnes of copper concentrate that was already stored there (First Quantum Minerals).

During 2025 the shipment of 122,520 dry metric tonnes of that concentrate generated about 312 million dollars in proceeds (Mining.com). The Government said the sale generated 29 million dollars in royalties, to be spent on public works (Mining.com).

Processing the stockpiled ore

On 7 April 2026 the company announced that the Government had approved the removal, processing and export of ore mined before the closure. The stockpile is estimated at about 38 million tonnes of ore, containing about 70,000 tonnes of recoverable copper. The company estimates the capital needed at about 250 million dollars (First Quantum Minerals).

The company's stated reasons include reducing the risks of leaving the ore stored on site for a long time, among them acid rock drainage (First Quantum Minerals).

Is this a reopening?

The Supreme Court, dismissing a challenge to the maintenance measure in 2026, said these actions do not mean a restart of the project's operations (La Prensa).

Civil society organisations disagree about where this leads. Earthworks and other international organisations have criticised what they call a proposal to reopen in order to close, and have called for communities to be consulted on what a safe closure means (Earthworks).