Illustrative model. Spektrum built this site from published sources to show how a Development by Consent process about the future of the Cobre Panamá mine could work. No such process has been agreed: not by the Government of Panama, not by First Quantum Minerals, and not by any community. Nothing here speaks for them.
A short account of the mine's history, from published sources.
The concession
In February 1997 Minera Panamá S.A. was granted the mineral concession under Contract Law No. 9, for twenty years with two possible extensions of twenty years each (Franco-Nevada (filing with the US Securities and Exchange Commission)).
In 2017 First Quantum Minerals raised its ownership of Minera Panamá to 90 percent (First Quantum Minerals). The other 10 percent is held by a Korean state resources company (Franco-Nevada (filing with the US Securities and Exchange Commission)).
2023: a new contract, protests and the court
On 20 October 2023 Law 406, approving a new concession contract, was published in the Official Gazette after the National Assembly approved it (First Quantum Minerals (press release)).
Large protests followed across the country. One account says some 250,000 people took part, more than 1,000 were arrested and four protesters were killed (CorpWatch). Another records 175 investigations opened and 60 people detained in relation to the protests (Business & Human Rights Resource Centre).
The President announced a referendum on the contract (CIAR Global). The Electoral Tribunal said it could not hold one (Energiminas).
On 28 November 2023 the Supreme Court of Justice ruled unanimously that the contract was unconstitutional. Among its reasons it referred to Panama's law on the rights of nature, Law 287 of 2022 (Eco Jurisprudence Monitor).
In December 2023 the Government formally ordered the mine to stop operating (Bloomberg).
Since the closure
In November 2023 First Quantum began arbitration against Panama before the International Chamber of Commerce and gave notice of a claim under the Canada–Panama Free Trade Agreement. On 31 March 2025 it agreed to discontinue the first and suspend the second (First Quantum Minerals).
On 30 May 2025 the company said the Government had approved a Preservation and Safe Management programme for the site, paid for by exporting 121,000 dry metric tonnes of copper concentrate stored there (First Quantum Minerals).
In September 2025 the Ministry of Environment announced a comprehensive audit of the mine (Ministerio de Ambiente (MiAmbiente)). Its final report was published in 2026 (Ministerio de Ambiente (MiAmbiente)).
On 7 April 2026 the company said the Government had approved the processing of ore that was mined before the closure and stockpiled on site (First Quantum Minerals).
In June 2026 the President named three ministers to a technical commission on the mine's future (La Prensa). A decision on that future has since been put back (Panama Times).